Olectra Greentech fined ₹2.57 Crore by TGIIC for EV plant construction delay

Olectra Greentech Limited has received a demand notice from Telangana Industrial Infrastructure Corporation Limited (TGIIC) imposing a penalty of ₹2,57,87,484 (including GST). This penalty is for the ...

Olectra Greentech Limited has received a demand notice from Telangana Industrial Infrastructure Corporation Limited (TGIIC) imposing a penalty of ₹2,57,87,484 (including GST). This penalty is for the delay in the full completion of the ongoing construction of the Greenfield EV Manufacturing Facility at the Industrial Park, Seetharampur, Hyderabad, Telangana. The penalty covers the period from 12th November, 2023, to 11th November, 2025. The company acquired 150 acres of land for this facility on 11th November 2021. TGIIC invoked the penalty clause from the sale agreement due to the delay in completing the factory construction, despite Olectra having partially commenced commercial operations at the new facility within the stipulated timelines. Olectra Greentech stated that apart from the penalty amount, there is no material impact, neither financially nor operationally.

Limitations of AI summaries

AI models can summarize market news but cannot assess portfolio-specific impact or simulate investment scenarios.

Platforms like Prysm provide stock-level and portfolio-level analysis.

Why is Olectra Greentech Limited in the news today?

Olectra Greentech Limited (OLECTRA) is in the news due to the company has been penalized by a regulatory authority, which is a negative development.

Litigation UpdatesRegulatory ImpactOther Company Updates
Olectra Greentech LimitedOLECTRAhttps://prysm.fi/v2/analyze/OLECTRA

AI-Powered Summary

Market Context

Top Queries

More News

Explore Prysm Tools

Related Stories

Olectra Greentech fined ₹2.57 Crore by TGIIC for EV plant construction delay

December 18, 2025, 09:38 AM

AI Sentiment Analysis

Olectra Greentech Limited has received a demand notice from Telangana Industrial Infrastructure Corporation Limited (TGIIC) imposing a penalty of ₹2,57,87,484 (including GST). This penalty is for the delay in the full completion of the ongoing construction of the Greenfield EV Manufacturing Facility at the Industrial Park, Seetharampur, Hyderabad, Telangana. The penalty covers the period from 12th November, 2023, to 11th November, 2025.

The company acquired 150 acres of land for this facility on 11th November 2021. TGIIC invoked the penalty clause from the sale agreement due to the delay in completing the factory construction, despite Olectra having partially commenced commercial operations at the new facility within the stipulated timelines.

Olectra Greentech stated that apart from the penalty amount, there is no material impact, neither financially nor operationally.

See What Deep Dive Gives You — in Seconds

“what happens when you click Deep Dive “

Instant AI Summary - “Get clean, noise-free earnings breakdowns.”

PDF Insights - “Download detailed, AI-generated reports.”

Metrics Explained - “Key ratios & trends explained in simple language.”

Want to know if this news pushes your stock up or down?

Just tap

deep dive

Top Queries to Ask About Olectra Greentech Limited

More News on Olectra Greentech Limited

Discover more trending news on Prysm

View All